Downtown Riverside's fall construction is finishing in a lopsided order. The projects that gate, remove or relocate things have dates, and most of those dates fall before the Festival of Lights switches on. The projects that add seats and gathering space have no confirmed date. If you live near the Mission Inn, here is what the next five weeks look like block by block.
The 34th Festival of Lights runs from Nov. 21 through Jan. 3, the Press-Enterprise reported on Oct. 5. This year it falls during the Mission Inn's 150th anniversary. The switch-on ceremony starts at 5 p.m. on Saturday, Nov. 21, at Orange Street and Mission Inn Avenue. Everything below is measured against that date.
The scorecard against Nov. 21
Councilmember Philip Falcone called it "A Season of Downtown Construction" in his Ward One column for the Riverside Downtown Partnership's October 2026 bulletin. The City's Public Works construction tracker, last updated Oct. 1, 2026, lists estimated completion dates for the biggest pieces.
| Project | Status or estimated finish | Ready by the Nov. 21 switch-on? |
|---|---|---|
| RTA stops moved to Market Street at 9th | In effect since Sept. 13, 2026 | Done |
| Fox Theater block refresh | New marquee and paint installed | Done |
| Whittier Place fence and gates | Estimated Nov. 9, 2026 | On track if the estimate holds |
| Civil Rights Walk | Estimated Dec. 28, 2026 | No |
| Main Street Alley | Promised "before the start of the Festival of Lights" | No confirmed date |
| Main Street Mall 60th-anniversary upgrades | Listed as planned in August | No confirmed date |
| Replacement seating on the California Tower block | "More information to follow" | No confirmed date |
The tracker's dates are estimates. Even so, the pattern holds. The first four rows move bus stops, repaint a block, gate an alley or tear up sidewalks. The last three would add tables, lights and shade, and none of them has a date.
What's already moved
The bus stops. Since Sept. 13, Riverside Transit Agency routes including 1, 12, 13 and 14 no longer use the stops on University Avenue at Market Street. They now stop on Market Street at Ninth Street, at stop 4830 or stop 4831. Which one depends on the route and direction, so check the line-by-line details in RTA's September 2026 service change notice before you head out. Falcone wrote that new concrete pads went in just south of the Fox for the relocation, and he credited the Riverside Downtown Partnership and the Greater Riverside Chambers of Commerce for working with RTA on it.
The Fox block. The Fox Performing Arts Center has a new marquee, a fresh coat of exterior paint and minor stucco repairs. The same painting project covers The Box, the Riverside Food Lab and the parking garage next door.
The California Tower tables. The Riverside Downtown Partnership's August 2026 bulletin said the table-and-chair units under the sunshades on the California Tower block had been removed. The sunshades and poles were slated to come out as well, with an installation planned to replace the seating and "More information to follow." The October bulletin doesn't mention a replacement.
Whittier Place finishes first, and it will be gated
Whittier Place is the alley between Albert S. White Park and the Center for Social Justice and Civil Liberties. It's the project most likely to be finished when the lights come on, with an estimated completion of Nov. 9 on a $295,700 fence-and-gate contract.
Falcone's October column says construction was set to begin this month and that the finished improvements "will expand the space and amenities available for the many festivals and special events held at Albert S. White Park."
The Riverside Community College District's Jan. 6, 2026 board packet gives the mechanics. The City, RCCD and the neighboring property owner agreed to vacate the public right-of-way and create a private alley with controlled access for those parties, their invitees and emergency services. The City is installing fencing and locked barrier gates at Chestnut and Market Streets, plus pedestrian gates with panic hardware for accessibility and emergency exit. RCCD is covering the estimated $289,156 initial construction cost from its Redevelopment Pass-Through Fund, and the City manages design, bidding and construction.
Neither document says when the gates will be open to the public. Before you plan a shortcut from Market Street to White Park during the festival, check with the City about how the gates will actually work.
The Civil Rights Walk runs into the festival's final week
The orange cones you've been stepping around belong mostly to the Civil Rights Walk, and the tracker doesn't expect it to finish until Dec. 28, 2026. That's five weeks after the switch-on and six days before the festival closes on Jan. 3. Unless the schedule speeds up, the busiest pedestrian weeks of the year will overlap with active sidewalk work.
The project is big. Falcone's column lists improvements at 109 locations: new ramps and sidewalk connections along two downtown loops, accessible pedestrian signals, leading pedestrian intervals, high-visibility crosswalks, LED warning signs, wayfinding, monuments, decorative signal wraps and four decorative crosswalk intersections. A City call for signal-wrap artists describes a 1.8-mile core loop and a 2.9-mile expanded loop. Wraps are planned at intersections that include Mission Inn and Main, Mission Inn and Lemon, Mission Inn and Lime, University and Market, University and Main, and 14th and Main. The loops connect landmarks such as Harada House, The Cheech, the Peace Tower, the Original Chinatown Site, Riverside City Hall and the Center for Social Justice & Civil Liberties–Miné Okubo Archive. The construction contract was awarded at $2,711,717.16.
Several of those intersections, including Mission Inn and Main, Mission Inn and Lemon, and Mission Inn and Lime, sit on the blocks around the hotel where festival crowds gather.
The projects that add space have no dates yet
The Main Street Pedestrian Mall dates to 1966, when parts of Main Street were closed to cars, as the Press-Enterprise noted in September. It turns 60 this November. Falcone's August column listed the anniversary projects as plans:
- Over-street café lighting and a large Riverside monument sign on Main between 5th and 6th Streets
- More trees and landscaping on Main between 6th and Mission Inn Avenue
- A public art installation made from the Mall's original 1966 Raincross streetlights, between Mission Inn and University Avenues
- The "Main Street Alley" between UCR Arts and Arcade Coffee Roasters
- Restoration work on City Hall
His October column covers the Civil Rights Walk, the Fox, the bus stops and Whittier Place, and it doesn't give a status for any of these items. The October bulletin's events list doesn't include a 60th-anniversary celebration either.
The Main Street Alley is the one with a public promise attached. The Raincross Gazette reported in late August that the alley off the Mall near 9th Street was fenced off and unused. It was created in 2019 when the Main + Nine apartment building went up. UCR owns the land, Arcade Coffee Roasters will open and lock it each day, and Public Works will maintain it. It will open only from Main Street. Falcone told the Gazette:
"Getting a table at Arcade Coffee can sometimes be a challenge due to how popular this shop is. The seating in this alleyway will add at least a dozen more tables and also will make this a usable event space for UCR Arts or others."
He also told the Gazette that the public could expect it to open before the Festival of Lights starts. Phase 1 is an arched "Main Street Alley" entry gate, tables and chairs, and large potted plants and trees. Café lighting, umbrellas, murals or banners would come in a second phase.
The dates you can plan around
Construction dates may slip. These have been set by their organizers:
- Saturday, Oct. 24, 9 a.m. to noon: a Slow Bloom Coffee x Hayet Albi pop-up at their soon-to-open shared space, 4019 Market Street, listed in the Raincross Gazette's October roundup. Hayet Albi landed there after its original site at 10th and Market fell through, the Raincross Gazette reported.
- Saturday, Oct. 24, 1 to 5 p.m.: Doors Open Riverside, at 19 locations in and near downtown. Tour times vary by site.
- Saturday, Oct. 24, 1 to 4 p.m.: the Mary S. Roberts Pet Adoption Center's Barktoberfest at White Park, a dog-friendly fundraiser with tastings from local craft breweries. VIP entry starts at noon.
- Sunday, Oct. 25: Pilates with Café Oro Dos Aztecas downtown, from the same Raincross Gazette roundup.
- Nov. 1–2 and Nov. 7: the downtown Día de los Muertos Festival, then the Veterans Parade from Riverside City College to the Historic Courthouse, according to the Raincross Gazette's 2026 events guide. Confirm both with the organizers closer to the date.
- Early November: Fleming's opens at 3777 Mission Inn Avenue, with a 107-seat main dining room, a bar, three private dining rooms and an outdoor patio, according to the October bulletin. Fleming's own page still says only "Fall 2026."
- Nov. 9: the estimated finish for the Whittier Place gates.
- Nov. 17: the deadline for downtown businesses to finish decorating windows for the Riverside Downtown Partnership's holiday window contest.
- Saturday, Nov. 21, 5 p.m.: the Festival of Lights switch-on at Orange Street and Mission Inn Avenue. New this year are Build-A-Bear Workshop pop-ups and bookable weekend Breakfast with Santa.
Two summer openings already have their seats: Orange Tree Tables and Taps, which held its grand opening July 7 at 3744 Main Street, and Notebook Cafe at 3512 Ninth Street. With the California Tower tables gone and the Main Street Alley still undated, the newer storefronts near the Mall are where the indoor seating is this season.
If you own a home near downtown and a season of cones, gates and moved bus stops has you thinking about selling sooner, Coko Acquisitions can make a cash offer within 24 hours and close on your schedule, whether that's before the switch-on or after the festival ends. Get My Cash Offer Now.